Project name: Raw Mill & Kiln line 3 Rehabilitation

  • Design & Fabricate over fly cable rack
  • Design the cable routing and replace the old cables
  • Supply new Power & Control cables required for the rehabilitation
  • Re-route existing Power & control cables from tunnel to the new cable rack
  • Pull & Install the new cable through new cable rack
  • Disconnect & reconnect the cables
  • Testing the cables after installation
  • Rotation, signal test & commissioning for RM & Kiln
  • Start up & reliability test
Category
Automation, Instrumentation and Control Systems
Date
October, 2019
Status
Completed