Raw Mill Subs HVAC Turn Key Project

  • Survey and collecting the existing RM Substation cooling System
  • Design & selection for proper Cooling Central Package Unit (PETRA), 45 cooling ton, 16000 CFM.
  • Sizing & Design of required ducting Routing
  • Supply The whole system including package unit, ducts & accessories
  • Installation for the complete system
  • Commissioning & start up
  • Reliability test and operation monitoring
  • Provide Training for client maintenance team