Project name: Installation of 25MVA Transformer for CM5
- Dismantle the old busbar duct
- Dismantle the old transformer HT Cables
- Dismantle of the old transformer
- Lifting out of the old transformer
- Civil modification for the support rails
- Connecting all parts for new transformer
- Lifting up and installation for the new transformer
- Connecting the HT side cables
- Install the HT Side bushing
- Connect the control cables
- Connecting the OLTC Power and Control Cables
- Connecting all sensor cables
- Erection for new power cables tray from transformer to the switch gear infeed
- Power cables 300mm single core termination and installation on transformer LT Side
- Vacuuming the transformer to be ready for oil refilling
- Filtration the oil by using filtration machine 6000 liter/hr
- Refilling the transformer by oil
Category
Installation and Commissioning
Date
July, 2020
Status
Completed